Bronagh English

The numbers

€450

A repair to the parapet, scheduled for 2017, and never carried out.

In 2014 the parapet was inspected as part of a formal principal inspection. Under Component 4, Parapets and Safety Barrier, the report reads:

“Some loose/missing stones and some repointing is required on both parapets.”

It scheduled two items of work:

ItemYearCost
K — Masonry repointing2017€250
J — Masonry repair2017€200
Total€450

€450. Scheduled for 2017. Never done — through a road reconstruction across that section in 2018 and a reseal of the approach in 2025.

Source: South Tipperary Eirspan Bridges, Inventory and Principal Inspection Report (ref TS-LP3101-001.00), O'Connor Sutton Cronin for South Tipperary County Council, issued 2014-03-04. Held on file, sha256 6af280d266a058ef…

Last updated 2026-08-05. This is a living record — findings are added as dated entries and prior versions remain visible.